Neptune's StaircaseLocks by Thomas Telford (1822), Banavie, Scotland

Neptune's Staircase, a locks by Thomas Telford in Banavie
Photo: Neptune's Staircase 20211023 by Daniel Kraft, CC BY-SA 3.0
Section through Neptune's Staircase, drawn to scale A long section through the eight locks at Banavie on the Caledonian Canal, rising about 20 metres in about 440 metres. The vertical scale is exaggerated four times. 8 locks · 8 × 180 ft · 440 m 64 ft · 20 m to Corpach (sea level) to Loch Lochy SECTION THROUGH NEPTUNE'S STAIRCASE Caledonian Canal, Banavie · eight locks in one flight · 1803 to 1822 · vertical scale ×4 050100 m
Horizontal scale and the eight 180 ft chambers are from published dimensions. The vertical scale is four times the horizontal, so the slope looks steeper than it is. Chamber depths are approximate.
Type
Locks
Built
1822
Where
BanavieScotland
Today
In use
Telford's part
Engineer
Location
56.8467, -5.0940approximate

Eight locks climb the hill at Banavie in one unbroken flight, lifting boats about 20 metres on the Caledonian Canal with Ben Nevis behind. It is the longest staircase lock in Britain, and it still works.

What you are looking at

In a staircase lock the top gate of one chamber is also the bottom gate of the next, so there is no pound of water between them. A boat leaves one lock and goes straight into the one above. Neptune's Staircase has eight, each 180 feet long and 40 feet wide, and together they raise the canal about 64 feet (20 metres) in a quarter of a mile or so. A boat takes around 90 minutes to climb or descend. The gates were originally worked by hand and have since been converted to hydraulic operation.

Telford and William Jessop chose to group the locks in clusters to cut costs. At Banavie that meant one great flight rather than a scatter of separate locks along the hillside. The West Highland railway crosses the canal at the bottom of the staircase.

Who built it

The Caledonian Canal was begun in 1803, after the government asked Telford how to slow emigration from the Highlands, and it opened in 1822. Telford was principal engineer and Jessop was consulting engineer. It took 17 years instead of the planned seven, and cost about £840,000 against an estimate of £350,000. When it opened it was only 14 feet deep, not the 20 feet Telford had planned, which was too shallow for many of the ships then being built. Work to deepen it followed in the 1840s.

Visiting

Check boat movements and facilities with Scottish Canals before you travel.

Questions people ask

How many locks are there at Neptune's Staircase?

Eight, in a single flight.

How much does it raise boats?

About 20 metres (64 feet). Some sources give 19 metres (62 feet).

How long does it take to pass through?

About 90 minutes.

Why is it called Neptune's Staircase?

It is a nickname for the flight of eight locks, which are built in a ladder formation.

Is it the longest staircase lock in Britain?

Yes. Other staircases exist, but none has as many chambers in a row.

Did Telford build the whole Caledonian Canal?

He was its principal engineer, with Jessop as consulting engineer. About a third of the route is man-made and the rest uses lochs Dochfour, Ness, Oich and Lochy.